Black house icon

Del Mar Underground Construction Project

Project Overview

Pasadena Water and Power installed underground conduits and vaults along Del Mar Blvd, between Michigan Ave and Oak Knoll Ave. This project addressed capacity issues and enhanced reliability on the City's electric sub-transmission system.

Timeline and Location

Work began in January, 2022, and concluded in May 2022. Construction impacted Del Mar Blvd, between Oak Knoll Ave and Michigan Ave.

Please reference the below map for the construction project location.

Contact Information

For questions, please contact Johnathan Giang, Associate Engineer at 626.744.7957, or send an email.