Black house icon

Distribution Voltage Conversion Projects

UPDATE: This project was completed in December 2024.

Two PWP workers in separate, extended buckets work on powerlines against a blue sky

PWP has an ongoing program to convert outdated 4kV distribution circuits in the city, along with their aging infrastructure assets, to 17kV while replacing and upgrading assets during construction.

The conversion projects will provide increased reliability, expanded system capacity, and improved power quality to customers. Poles, transformers, and conductors will also be replaced or upgraded in the construction process, providing new assets to last for the long term.

Timeline and Location

From October 1 to November 15, work on a conversion project will take place on El Sereno Avenue and Navarro Avenue, between Howard Street and Montana Avenue, including small adjacent sections of Tremont Street. Another such conversion project is planned for the streets of Newport Ave., Mentone Ave., Belmont Ave., Glen Ave., Wyoming St., Idaho St., and Stanton Ave., between Howard St., and Montana Ave. This project is scheduled to run from October 1 to December 13.

Two outages will be necessary to complete the project. One short outage, approximately 2 hours in length, will be required to swap service connections, when crews replace transformers, low voltage conductors, and service drops. Dates of outages at any specific address are unknown currently, but when construction crews progress through the project additional notifications will be sent out. A final longer outage of 6-8 hours will be required at the end of the project, to cut the newly replaced infrastructure over to the new 17kV circuit feed point.

UPDATE September 2024: Temporary no street parking signage will be present localized to the small area where vehicles need to be staged at the active point of construction. The no parking signage will move as the project progresses down the street. Driveways will remain open during construction.

Construction crews will coordinate with Public Works Solid Waste regarding trash pickup in the area.

PWP strongly recommends that customers in the neighborhood review our outage preparation tips.

Recently Completed Conversions

  • A conversion project in Temple Alley, and a neighboring block, between Hill Ave., and Sinaloa Ave., was completed on June 24th.