Fillmore Street Water Main Replacement

This project was completed in August 2026.

Seven PWP construction workers in reflective vests and white hard hats stand in and around a trench on Fair Oaks Avenue. It is dark outside with work lamps shining spotlights onto the trench.

The Fillmore Street Water Main Replacement project will involve the installation of a new 8-inch diameter water mainline in Fillmore Street from Fair Oaks Avenue to Raymond Avenue. The pipeline will facilitate the water service upgrade the overall reliability and quality of water service in Pasadena.

Timeline and Location

Construction activities will occur in three phases for different locations:

  • Phase I (July 20 to 24) - Nighttime construction on Fair Oaks Avenue and Fillmore Street. The intersection of Fair Oaks Avenue and Fillmore Street will be closed, with detours routed through Bellefontaine Street and Raymond Avenue. Please see map below for reference.
  • Phase II (Beginning July 27): Daytime construction in Fillmore Street. The eastbound travel lane on Fillmore Street will be closed; the westbound travel lane will remain open.
  • Phase III (Concluding end of August): Daytime construction at the intersection of Raymond Avenue and Fillmore Street. There will be partial lane closures but a minimum of one lane in each direction on Raymond Avenue will remain open to traffic.

During construction, a variety of heavy equipment will be used including excavators, backhoes, loaders, and construction trucks. Traffic signs and delineators will be employed to minimize the impact of traffic flow along Fair Oaks Ave, Fillmore St, and Raymond Ave. Please observe and adhere to posted no parking zones, construction signs, and flagmen. Special efforts will be taken to keep inconveniences to a minimum.

Impact

No interruptions to water service are currently scheduled. Nighttime work during Phase I will occur from 10 p.m. to 6 a.m. Daytime work during Phase II & III will occur from Monday to Friday from 9 a.m. to 4 p.m.

A map of the area around Fillmore Street and Fair Oaks Avenue in southern Pasadena. An inset highlights a detour route for the blocked off intersection of Fillmore and Fair Oaks. Drivers headed northbound on Fair Oaks are re-routed to make a left on Bellefontaine, then head north on Pasadena Avenue to reach California Boulevard. Drivers headed south on Fair Oaks are re-routed to make a left on California and a right on Raymond Avenue until they reach Glen Arm.
Overnight construction will feature detours on Bellefontaine Street and Raymond Avenue.

Contact Information

Please contact Norman Lara at NLara@CityOfPasadena.net or (626) 744-7607