Mentor Avenue Water Main Replacement

Two PWP construction workers in hard hats and reflective vests peer into a trench

The Mentor Avenue Water Main Replacement Project will replace and upgrade aging underground water infrastructure to support water service reliability in the area.

Timeline and Location

Construction activities will occur on Mentor Avenue in two phases:

  • Phase I: October 26, 2026 through January 2027 - Between San Pasqual Street and Del Mar Boulevard
    • Construction will be paused in November 2026 until the new year during the City's construction moratorium.
  • Phase II: Completion of Phase I through June 2027 - Between Green Street and Union Street.

Construction timelines may be impacted by inclement weather.

 

Impact

Construction will feature intermittent lane closures with at least one lane open to traffic. Driveways will remain accessible. Construction hours are Monday through Friday from 7 a.m. and 4 p.m.

Traffic signs and delineators will be employed to minimize the impact of traffic flow in the area. Please observe and adhere to posted no parking zones, construction signs, and flagmen. Special efforts will be taken to keep inconveniences to a minimum.

PWP crews will notify residents with door hangers one week in advance and give courtesy door knocks the morning of interruptions.

Contact Information

Please contact Water Operations Section Supervisor, Norman Lara, at NLara@CityOfPasadena.net or (626) 744-7607