Oak Knoll Water Main Replacement Project
This project was completed in April 2026.

Pasadena Water and Power is replacing a water main on Oak Knoll Avenue that has been in service for more than 100 years. An 8-to-6 inch line will be replaced by an 8-inch ductile iron mainline pipe to reinforce the reliability of PWP's water service.
To minimize the impact of this project on residents and businesses in the area, construction efforts will be contained to approximately one block at a time. Construction will intermittently affect water service, and notice of any water interruption will be provided at least 48 hours in advance. Special efforts will be taken to minimize customer inconvenience.
During construction, a variety of heavy equipment will be used including excavators, backhoes, loaders, and construction trucks. Temporary traffic control and detour signs will be posted at all times during construction. Most work will occur Monday through Friday, from 7 a.m. to 4 p.m. Please note businesses in the area will remain open and accessible during construction.
Timeline and Location
Construction will begin in May 2025 and is currently scheduled to complete by April 2026. The project affects Oak Knoll Avenue spanning from Colorado Boulevard to California Boulevard. Please reference the map below for the construction project location.