Path 2 Transmission Cable Upgrade

A PWP worker lowers a toolbox into an underground electrical vault

The Path 2 Transmission Cable Upgrade Project is scheduled to begin in mid-October. Cable that is nearing the end of its service life is being removed, followed by the immediate installation of new, maximally sized cable. This project will significantly increase the capacity and reliability of the PWP electric system.

This increase in capacity and reliability supports the integration of renewable energy resources into Pasadena's grid, advancing the City’s goal of achieving 100% carbon-free energy by 2030.

Timeline and Location

The project will span roughly five miles traversing the city on section of South Fair Oaks Ave., East Del Mar Boulevard, Roosevelt Avenue, and East Walnut Street.

A map of the entire route of Path 2. It stretches from the southwest at the the corner of Fair Oaks Avenue and Glenarm Street, proceeds north on Fair Oaks, heads east on Del Mar Boulevard, passes CalTech and Pasadena City College, heads north on Roosevelat Avenue and finally heads east on Walnut Avenue before stopping just past Altadena Drive.

The project is scheduled to begin on Monday, October 19th, with working hours in accordance with City ordinance. Work is currently scheduled to complete by the end of May 2027.

Impact

Light to moderate traffic control will be enforced in the immediate area around workers and equipment. Localized no parking signage will be deployed and move with the active construction area and are expected to be enforced for one to two days at a time.

Driveway access will be maintained in the vast majority of circumstances and in special cases, access around the working areas will be directly coordinated with impacted customers.

Direct impact and working areas will remain small as it progresses through the outlined route.

Contact

For questions, contact Jacklin Ghaly at JGhaly@CityOfPasadena.net.