Wallis Street Water Main Replacement

A Pasadena Water and Power worker in a white hard hat and neon yellow reflective vest stands in a ditch with a tool. He is looking down at an uncovered section of yellow pipe.

The Wallis Street Water Main Replacement Project will replace a nearly 100 year-old water 6 inch pipe with an 8 inch ductile iron pipe. The newly upgraded water main will support reliable water services in the area.

Timeline and Location

Construction activities will occur on Wallis Street between South Marengo Avenue and South Los Robles Avenue. Construction is scheduled to begin on July 20, 2026 and completing in early October 2026. See the map below for further details.

A map highlighting Wallis Street at the north border of Allendale Park and Allendale Elementary. The highlight stretches from Marengo Avenue in the west to Los Robles Avenue in the east.

Traffic signs and delineators will be employed to minimize the impact of traffic flow in the area. Please observe and adhere to posted no parking zones, construction signs, and flagmen. Special efforts will be taken to keep inconveniences to a minimum.

Impact

Currently, work is planned on two different schedules:

  • Before August 17
    • Monday through Friday - 7 a.m. to 7 p.m.
    • Saturday - 8 a.m. to 5 p.m.
  • After August 17
    • Monday through Friday - 9 a.m. to 2 p.m.
    • Saturday - 8 a.m. to 5 p.m.

Interruptions to water service will occur toward the end of the project timeline. PWP crews will notify residents with door hangers one week in advance and give courtesy door knocks the morning of interruptions.

Contact Information

Please contact Water Operations Section Supervisor, Norman Lara, at NLara@CityOfPasadena.net or (626) 744-7607